Case Studies
RC Homes: "Roscoe"
A power utility could not agree on a conflicting set of rules, telling builder they must relocate project switchgear from front to rear yard. C of O was due that week and buyers set to move in. Seawolf got resolved this in 3 business days without having to move equipment.
Greenpointe: “Kentish Town”
New buyer to close within one week, contingent upon C of O. C of O had been promised in one week but already taken 45 days. Seawolf was hired only to obtain C of O within 5 business days, but upon engagement with City utility, discovered the cause of the delays: open grading, plumbing, and supplemental structural permits. If the delays weren’t resolved in 5 days, the buyer was ready to walk away. Seawolf got the grading permit issue resolved in two days; plumbing in one day. The supplemental permit, which required a new submittal, was reviewed and approved in two business days. C of O was issued within 5 days.
Gibson Overseas: “South Fig”
After all utility project approvals had been given and final inspections were to begin, a rogue utility inspector appeared onsite and documented that, among 19 other corrections, the project’s bus duct needed to be relocated and the coldwater grounding needed to be reworked. Seawolf's diplomatic resolutions allowed the project to continue without litigation.
Gemdale: “235 N Hoover”
Client was set to begin trenching, but utility was doing trunkline water work on the same street when they arrived. Initial review revealed builder would have to re-do power design process, moving trench 5 feet from water line. Seawolf brought water and electric departments together in 3 days, identifying and resolving an issue which could have otherwise taken months.
Meritage: “Cabrilla”
Gas utility parts shortages were making builders wait 2+ months until parts arrived. Seawolf got parts delivered and prioritized for the builder, installing parts in 3 days.
RC Homes: “Sage at Ninth”
Utility crews were non-responsive on meter installation date. After weeks of waiting, Seawolf got meters installed in 2 days.
TDC Properties: “Berendo”
After two months waiting for utility inspector to return calls, Seawolf got the inspector to visit the jobsite and approve work the next day.
Carmel Partners: “Bundy Drive”
Expedited City Traffic Control Plan, from quoted 4-6 months to 3 days.
Dry Utility Experts: “West Adams”
Expedited City trenching plan, from quoted 1 month to 5 days.
Crescent Capital: “Gillis House”
Expedited City u-permit issuance, from quoted 4 months to 10 days.
Gemdale: “235 N Hoover”
Expedited review of City department tree conflict with proposed trenching plan, from unknown number of months—but typically 6 or more—to 5 business days. Inspector on-site within 2 days.
Greenpointe: “The Hollywood Flats”
Expedited Utility construction crews beginning work, from quoted 6-8 weeks to 2 days.
TrueLife Companies - "El Sereno"
Services provided:
Grassroots Organizing for Area Planning Commission
Outcome: WIN. Seawolf brought out dozens of supporters who hailed the project, tipping the scales in favor of the builder.
Shea Homes: "Arroyo HP"
Services provided:
Permit expediting
Outcome: WIN. The first hurdle was resolved in two days, and the second within a week.
Watt Communities: "Coolidge Place"
Services provided:
Permit expediting
Outcome: WIN. Identified the bottleneck within one day and obtained C of O within three days.
Watt Communities: "Autry"
Services provided:
Permit expediting
Outcome: WIN. One call to Seawolf opened doors. We resolved the issue within five days.
Fassberg Contracting: "1717 Western"
Services provided:
Permit expediting
Outcome: WIN. Seawolf worked with the local utility to obtain delivery of design in a fraction of the amount of time as originally quoted.
Gibson Overseas: "1400 S Figueroa"
Services provided:
Permit expediting
Outcome: WIN. Seawolf worked with the local utility to obtain a fire pump meter release, get the project energized, and navigated enormous, unforeseen political hurdle.
LINC Housing: "The Spark"
Services provided:
Permit expediting
Outcome: WIN. Seawolf worked with the local utility to obtain power one to two months ahead of schedule…we even beat our own goal by two weeks!